Document Number PM / PR / 002
Revision 03 Effective Date 1 August 2003 Page 2 of 4 Copy Number Tooling Management (New / Transfer)
1. Objective
To establish a procedure whereby all new / transferred tooling are received and maintained. 2. Scope
Applies to all new production tooling or transferred tooling from customers and associates. 3. Procedure Flow
Responsibilities
3.1 Production
Engineering
Procedure Outline
Receive new tooling Inform Project Engineering of
any non-conformance Raise Work Order to vendor’s
Tool-Room Transport tooling to vendor’s
Tool-Room Review Tooling checklist
Interfaces
Delivery Order Project Engineering Tooling Work Order
(Form/C/TL/008) Tooling Checklist
3.2 Production
Perform Mold testing
Mold Testing Request
(Form/I/EN/016) Molding Process Determination
Form (Form/I/PD/039)
Tooling Checklist Molding Data Sheet
(Form/I/PD/008)
Tooling Mold Life Records
3.3 Production
Engineering
Update records
Private & Confidential
Intec Manufacturing (Asia) Pte Ltd
Document Number PM / PR / 002
Revision 03 Effective Date 1 August 2003 Page 3 of 4 Copy Number Tooling Management (New / Transfer)
4. Procedure Details
4.1 Production Engineering
4.1.1. Receive and check new / transferred tooling for any visual damage. Acknowledge the
Delivery Order if tooling is in good condition. In the event when any non-conformance is discovered, inform Project Engineering. Project Engineering is to follow up with supplier / customer.
4.1.2. For transferred tooling, raise work order and route the tooling to vendor’s Tool-Room for
inspection and marking / numbering.
4.1.3. Upon receiving the tooling from vendor’s Tool-Room, review the Tooling checklist and if it
is a new tooling, review tooling report together with Project Engineering & Production. Liaise with Project Engineering and Production Control for mold testing.
4.2 Production
4.2.1. Perform mold testing and record the data in the Molding Process Determination Form. 4.3 Production Engineering
4.3.1. Update Molding Data Sheet.
4.3.2. Update Tooling Mold Life Records. 4.3.3. Update Tooling Checklist.
Private & Confidential
Intec Manufacturing (Asia) Pte Ltd
Document Number PM / PR / 002
Revision 03 Effective Date 1 August 2003 Page 4 of 4 Copy Number Tooling Management (New / Transfer)
CHANGE RECORD
Description of Change
1. Re-write to reflect new practices and remove redundancies. Introduce new format.
1.1 This procedure was part of Tooling Management (Production), it has now been split into 2
separate procedures.