您的当前位置:首页河道治理边坡水毁修复处理施工方案

河道治理边坡水毁修复处理施工方案

2021-10-25 来源:爱问旅游网


河道治理边坡水毁修复处理施工方案

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件 目录 1.工程剖

析········································································································1 1.1工程说

明·······················································································································1 1.2工程地

质·······················································································································1 1.3水文气

象·······················································································································1 1.4合同项目及工作范

围·····································································································1 1.5工期及工程控制性进

度·································································································2 1.6质量与安

全···················································································································3 2.施工总布

置····································································································5 2.1施工总体布置条件及原

1 / 35

则·····························································································5 2.2场内施工道路布

置········································································································6 2.3施工供风与供

水············································································································7 2.4混凝土拌合系统混凝土生产系

统···················································································7 2.5施工供电、照明、通

信·································································································8 2.6办公及生活福利设

施···································································································11 2.7渣

场····························································································································11

2.8其他生产辅助设

施······································································································12 2.9施工消

防·····················································································································14 2.10施工保

险···················································································································15 3.施工进度计

2 / 35

划·······························································································16 3.1编制依据与原

则··········································································································16 3.2招标文件施工总进度要

求···························································································16 3.3施工总进度计划安

排···································································································17 3.4施工关键线

路··············································································································17 3.5工程进度控制重点及措

施···························································································18 3.6工期保证措 施··············································································································18 4.组织机构及资源配

置····················································································22 4.1施工进

场·····················································································································22 4.2现场施工准

备··············································································································22 4.3现场组织机构设

置······································································································23 4.4具体管理措

3 / 35

施··············································································································26 5.土方明

挖······································································································28 5.1工程概

况·····················································································································285.2施工布

置·····················································································································28 5.3土方开挖施

工··············································································································29 6.石渣填筑施

工·······························································································32 6.1填筑施

工·····················································································································32 6.2土方填筑机

械··············································································································35i 格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程技术文件 6.3施工排水及防洪度

汛···································································································35 7.混凝土工

程··································································································37 7.1施工项目和主要工程

4 / 35

量·······························································································37 7.2施工依

据·····················································································································37 7.3施工布

置·····················································································································38 7.4模板工

程·····················································································································38 7.5钢筋工

程·····················································································································41 7.6预埋件工

程·················································································································44 7.7混凝土施

工·················································································································45 7.8结构缝施

工·················································································································47 7.9混凝土的缺陷修

补······································································································48 7.10质量、安全保证措

施·································································································49 7.11混凝土施工主要机械设备和人员配 置·······································································51

5 / 35

8.质量管理体系及保证措

施·············································································52 8.1质量目

标·····················································································································52 8.2施工质量管理保证体

系·······························································································52 8.3工程质量检

验··············································································································55 8.4主要工程质量控制措

施·······························································································56 9.安全生产保证体系及措

施·············································································58 9.1安全方针、目

标··········································································································58 9.2安全保证体

系··············································································································58 9.3安全生产管理重

点······································································································60 9.4安全保证措

施··············································································································61 9.5安全应急救援预

6 / 35

案······································································································68 10.环境保护与文明施

工··················································································72 10.1环保、水保保护目

标·································································································72 10.2环境保护、水土保持组织机

构··················································································72 10.3环境保护、水土保持管理检查制

度···········································································72 10.4环境保护措

施············································································································73 11.附

件···········································································································76ii 格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件1.工程剖析 1.1工程说明

格里桥水电站位于贵州省贵阳市开阳县与黔南州瓮安县交界的清水河干流上。其下游接构皮滩水电站,距清水河出口约44km,上游接大花水电站梯级,距大花水电站厂房区约19.5km,装机容量2×75MW,距贵阳约108km。

格里桥厂房上游侧边坡坡脚受2015年7月16日泄洪冲刷影响,导致厂房上游侧658m高程至河床边坡被冲刷破坏,为保证上游边坡及出线塔架基础的稳定。拟采用钢筋混凝土护坡对已冲刷损毁的边坡进行修复处理。

7 / 35

1.2工程地质

格里桥厂房上游侧边坡基岩为逆向坡,地层岩性为为吴家坪(P2w3)薄层至厚层硅质岩与页岩、炭质页岩互层夹燧石灰岩,局部夹层厚度达

0.15~1.8m,边坡岩体为弱风化岩体及微新岩体,岩溶不发育,受风化及裂隙的影响,岩体较为破碎。排水洞出口至厂房尾水渠上游导墙部分边坡为覆盖层及石碴回填边坡,坡内有大孤石及零星基岩出露,覆盖层深槽部位有钢筋混凝土灌注桩承台基础。河床水位约为619m~627m,河床内有泄洪后两岸垮塌的碴料及大块石。

1.3水文气象

清水河流域属于亚热带季风气候区,夏季受太平洋副热带高亚控制和西南海洋性暖湿气流影响,冬季主要受西风北支急流的影响,气温和降水四季变化明显,冬季气温低而干燥少雨,夏季气温高而湿润多雨。本流域多年平均降水量在1000m~1350mm之间,年内分配极不均匀,4~10月占全年降水量的86.5%,而12月、1月、2月降水量只占5.4%。

格里桥坝址5月~9月平均气温超过20.0℃,年内7月气温最高,1月最低,最高气温39.3℃,最低气温-6.2℃。

1.4合同项目及工作范围 1

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件

1.4.1本标应完成的主要工程项目

我公司应完成的主要工程项目有(但不限于):、

(1)开挖工程:边坡清理开挖,护坡混凝土基础开挖,河道疏浚;(2)石渣回填工程;

8 / 35

(3)混凝土工程:贴坡混凝土,毛石混凝土挡墙,挡墙回填;(4)排水工程;落水井、排水管、排水沟等;

(5)施工临时工程:施工便道修建及维护;线路接入点至本标施工供电设施的施工、运行及维护及其他临建工程建设及维护。

1.4.2本包主要工程量

土方明挖40471m3,石渣回填26749 m3,混凝土浇筑4086m3,主要工程量见表1.4-1。

1.5工期及工程控制性进度1.5.1施工工期 2

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件

本合同工程开工时间为2014年4月1日,完工时间为2015年5月25日,总工期55天。高程EL.637.5m以下支护于2014年4月30日前完成。

按招标文件要求时间完成。 1.5.2施工程序

本标工期较紧,单位时间完成工作量大,为确保工程按期完工,将现场划分为以下5个区域流水作业:

1#区域:高层:EL.637.5m以下,桩号:挡墙0+035.1m至下游侧;2#区域:高层:EL.637.5m以下,桩号:挡墙0+035.1m至上游侧;3#区域:高层:EL.637.5m以上~3#公路平台,桩号:挡墙0+035.1m至下游侧;

4#区域:高层:EL.637.5m以上~3#公路平台,桩号:挡墙0+035.1m至下游侧;

5#区域:高程:3#公路平台以上;

9 / 35

主要施工步骤为: (1)边坡表沉清理;

(2)面板混凝土基础开挖;同时进行河道疏浚开挖;

(3)1#区域不需回填部分支护施工;同时进行2#区域石渣回填;(4)2#区域支护施工;同时进行1#区域石渣回填施工;

(5)1#区域回填部分支护施工;同时进行3#区域石渣回填;(6)3#区域支护施工;同时进行4#区域石渣回填;

(7)河道疏浚完工,4#区域支护施工;同时进行5#区域挡墙及排水沟施工;

(8)5#区域回填及支护施工; (9)路面混凝土施工;植被恢复施工; (10)完工验收。 1.6质量与安全

施工质量是工程成败的关键,是企业赖以生存的生命线。 我公司对工程产品质量的管理体系完全按照GB/T19001-2000 idt3 格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件ISO9001:2000国际标准质量体系执行。因此,在工程施工中,我项目部将严格遵守招标文件中对质量管理体系的要求,严格执行GB/T19001-ISO9001:2000《质量管理体系》系列标准,确保本工程质量目标的实现。

本合同工程项目质量目标为:单元工程合格率100%,土建单元工程优良率85%以上;杜绝质量事故,并遵守、执行发包人和监理人的质量管理文件;确保工程质量达到设计规范的要求。

10 / 35

施工中认真贯彻“安全第一、预防为主”的方针,杜绝施工中的人身伤亡事故和重大机械安全事故,使轻微伤害频率低于行业标准。

4

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件2.施工总布置 2.1施工总体布置条件及原则 2.1.1施工总体布置条件 (1)交通条件

本标位于格里桥发电厂上游侧,可利用场区内已有的公路系统,结合现场实际情况布置施工便道至工作面。

(2)施工临时工程和施工辅助设施:

1)本标段砂石采用外购,不需要修建临时砂石系统; 2)临时拌和系统;

3)弃渣场场地(碴场位于原砂石系统处堆弃,运输距离约2km);4)施工用电接入点(格里桥电站厂房内);

5)施工用水(清水河内抽取) (3)施工条件

本工程主要建设物资初步拟定从贵阳市、开阳县供应,主要的物资来源情况如下:

钢材:拟由贵阳市场供应,公路里程108km。

水泥:拟从贵阳供应,公路里程108km。砂石料:拟由当地供应。 木材:拟由当地供应。

11 / 35

油料:拟由当地供应。

火工产品:炸药、雷管、导火索、导爆管全部拟由开阳县供应。 2.1.2施工总体布置原则

结合本工程的施工条件、施工环境及施工特点,确定本工程的施工布置原则为:

(1)所有的临建设施、施工辅助企业及施工道路均按招标文件要求以及业主提供的各种条件在指定的施工场地内进行规划布置;

5

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件(2)临建设施的规模和容量按施工总进度及施工强度的需要,力求布置紧凑、合理、方便使用,集中管理、调度灵活,规模精简,以期降低工程造价;

(3)施工布置充分考虑各单项工程的相互关系、施工手段和进度形象,保证各环节的措施到位,施工过程合理有序,以充分发挥施工设备生产能力,满足施工总进度计划要求;

(4)充分利用业主为本合同工程提供的场内、场外交通、场地、通讯以及能源等施工条件;

(5)在本工程需新建的场内施工道路规划布置上,应尽可能地避免影响发包人通行;

(6)根据地形情况,尽量做到挖填平衡,尽量减少临建工程量;(7)各施工厂区及生活营地均按有关规范要求配置足够的环保设施及消防设施;

(8)积极响应招标文件,满足招标文件的各项要求。 2.1.3施工用地计划

12 / 35

施工场地布置详见投标附图《施工总平面布置图》,施工临时用地见表2.1-1。

2.2场内施工道路布置

根据本标段施工现场总体布置需要和地形条件,充分利用场区内已形成的公路系统,自厂房上游3#进场公路位置修建一条施工便道至河道清淤工作面,详见施工总平面布置图。

6

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件

2.3施工供风与供水2.3.1施工供风

本标工程采用2台3.5m3/h移动式柴油空压机供风。施工供风系统布置特性见表2.3-2。

2.3.2施工供水

本工程施工供水主要包括混凝土临时拌和系统、施工营地、混凝土养护用水等。其中:混凝土临时拌和系统,施工营地用水可利用原布置供水系统,混凝土养护用水现场布置1个5m3移动水箱供应。2.3.2.1废水处理

拌和站等部位的施工废水,经过排水沟进入沉淀池,采用自然沉淀法处理,经过泥浆风干后,用自卸汽车运出,最终清水达到排放标准后排入河中。2.3.2.2施工营地生活供水及消防备用水

施工营地生活用水及消防备用水采用原布置供水系统供应。施工供水系统主要设备及材料见表2.3-3。

2.4混凝土拌合系统混凝土生产系统2.4.1施工生产任务

根据招标文件,本工程混凝土主要包括面板护坡混凝土、排水沟、路面及挡墙修复混凝土、边坡菱形框架混凝土等,混凝土总量约为4086m3。

13 / 35

2.4.2生产规模

根据施工总进度计划及混凝土强度施工要求,结合我公司现有设备情况,选

7

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件

择一台JS500型搅拌机,人工配料。 2.4.3工艺及布置

混凝土搅拌系统布置在原大坝施工混凝土拌合站位置,占地面积约100m2,拌合机型号为JS500型,混凝土生产率为15-18m3/h,骨料通过电子秤称量后,通过卷扬提升料斗进入拌合机。拌合站采用袋装水泥,人工拆包称量后卸入拌合机提升斗。

混凝土生产系统用水由原拌合站供水系统提供。水、外加剂经流量计计量后进入搅拌机。

袋装水泥库利用原拌合站附近仓库存储,水泥储存容量为50t,水泥库采用脚手管简易结构,四周围护并做好防雨防潮措施。

2.5施工供电、照明、通信2.5.1施工供电

根据招标文件,施工及生活用电由格里桥电厂有偿提供,由格里桥电站厂房内接至施工现场。

2.5.2施工照明 2.5.2.1照明布置

本工程施工照明电源采取分散供电,即各工作面照明用电电源由布置在附近的现场配电箱供应,以减少照明线路架线距离和降低电压损失。

14 / 35

施工现场采用高压镝灯集中照明,采用自制灯架装设镝灯,局部工作面采用碘钨灯加强照明。

办公及生活福利区、辅助施工部位、仓库等地面施工场地作业面采用工厂灯及投光灯集中投射照明,局部照明采用白炽灯。

施工照明主要设备、材料参见表2.5-4。 8

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件

在施工作业区、施工道路、临时设施、办公区和生活区设置足够的照明,其照明度不低于表2.5-5的规定。

2.5.2.2线路敷设

电线在敷设前认真检查,电线外观应无损伤,用500V兆欧表进行绝缘测量,绝缘良好符合规范要求。电线敷设时应从电缆绞盘的上端引出,不能在电线支架上及地面上摩擦拖拉。电线直埋或在保护管中不得有接头。在布线的同时进行接地体的安装,接地体采用搭接焊。扁钢搭接长度不得小于扁钢宽度的2倍;圆钢搭接长度不小于圆钢直径的6倍;圆钢与扁钢搭接时,搭接长度为圆钢直径的6倍;扁钢与角钢连接时,应在其接触部位两侧进行焊接。

在布线及接地完成后及时通知监理工程师现场检查验收,合格后进行灯具安装。灯具应由具备资质证书的测试单位进行抽样测试,测试应符合现行国家标准《灯具安全要求与试验》,抽样测试合格后按照灯具安装说明进行安装。各电缆干线、支线接头处理必须符合《城市道路照明工程施工及验收规范》的相关规定。

2.5.3接地及避雷装置

在本标段中,根据国家标准结合施工现场年均雷暴天数及生产区域特点,一级防雷区域为:油库;二级防雷区域为:生活营地、配电房;三级防雷区域为:

15 / 35

9

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件拌和站、仓库、加工厂、空压站。 2.5.3.1防雷接地装置的安装要求: (1)接地装置的接地电阻不得超过4Ω;

(2)接地极不能少于2根,2.5米一根植入地下,掩埋深度不小不小于500mm,应广泛利用天然接地极,如与大地有可靠连接的房屋和建筑物等的金属构架及水管等(但有爆炸危险及可燃性气体管道除外);

(3)接地线与接地极的连接应用焊接或压接,搭接焊缝不小于300mm,连接处设置短线卡子应便于检查;

(4)接地装置安装完毕后,应用“接地电阻测定器”测试其接地电阻是否符合规定。

2.5.3.2防雷接地措施

在本次电气设计中,为了预防雷害,根据施工区域的实际情况,采取以下防护措施:

(1)在生活营地建筑物上设置避雷带,与电气接地可靠连接。浴室等用电安全隐患大的部位设置等电位连接;

(2)对于拌和系统在防雷、电气接地的同时应另外单独设置接地区(接地电阻不大于4Ω)供计算机接地;

(3)对于油库,应根据地形设置避雷针(避雷针接地冲击电阻不大于10Ω),为避免雷电反击,避雷针离被保护物距离不小于5米;(4)拌和系统的防雷接地与电气接地进行可靠连接;

2.5.4施工电气设备的安全用电措施 2.5.4.1供电安全

16 / 35

由于施工区域用电设备数量较多,且相互交叉作业,如果使用不当和缺乏必要的保护措施会造成不应有的事故,因此对用电设备采取一定的安全防护措施很有必要。在本次施工供电中,对用电设备主要采取以下安全措施:

(1)本标段供电系统采用三线四线制供电(TN-S),在重点区域如:生活营地采用三相五线制供电(TN-C-S);

(2)所有用电终端必须装设漏电开关,开关漏电动作电流根据实际情况选定;

(3)对于裸露的带电部分或绝缘性不足以保证安全的部位,应加设防止接近

10

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件

的措施,同时标以醒目的“危险”或“注意安全”等标志;(4)定期对各种电气设备进行工频耐压实验,以确保使用安全;(5)禁止在设备零线上安装熔断器或单独的断电开关。2.5.4.2备用电源措施(1)在配电所配置一台30kW柴油发电机,保证长时间停电期间生产系统的照明用电和安保用电。

2.5.5计量装置

采用低压侧计量。在本标段的电气设计中,在各配电室400KV电源母线进线处安装低压计量箱,以满足计量要求。

施工现场计量采用低压计量方式,有功电度表装设于现场配电箱中。 2.5.6施工通讯

配置2台健伍无线对讲机满足施工期间,生产指挥、调度及流动用户通讯需要。平常用移动电话联系

2.6办公及生活福利设施

17 / 35

为满足工程现场施工生产及管理的需要,需在施工场地附近规划的施工营地范围布置相应的办公及生活临时设施。根据施工总体进度安排,本标段高峰期开挖强度为1000 m3,施工高峰人数约为54人,需相应的办公及生活福利设施建筑面积为130m2。主要办公及生活福利设施建筑特性见表2.6-6。

2.7渣场 11

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件

根据招标文件要求,本标段的开挖弃渣料,有用料主要用作边坡石渣回填,余料及无用料弃至马路河碴场。所有开挖均采用CAT320挖机开挖,辅助人工清坡,渣料采用挖机CAT320挖装,25t自卸汽车运渣。弃渣运输距离约2km,填料运输距离平均500m。

2.8其他生产辅助设施

本标段其他生产辅助设施的规模和容量按施工总进度及施工强度需要设计,力求布置紧凑、合理、方便使用,集中管理、调度灵活、规模精简,以期降低工程造价,并尽量避免与其它标段工程施工产生干扰和影响。

其他生产辅助设施主要包括修理厂、钢木加工厂、试验室、综合物资仓库等,大部分临时辅助设施均集中布置。

2.8.1修理厂及机械设备停放场

修理厂主要承担各种机电设备、施工机械和汽车的日常维修与保养工作,设备大修及配件加工考虑在工地外进行。厂内设有工具材料库等,总建筑面积20m2,结合设备停放场占地面积为120m2。

2.8.2综合加工厂

18 / 35

钢筋和木材加工厂布置渣场内侧,主要承担本工程全部混凝土钢筋、土钉、插筋等的加工制作,并承担特殊部位的异形木模板、临建工程及其它木材加工,建筑面积为80m2,主要设备配置参见表2.8-7。

12

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件 2.8.3试验室

根据本标要求,现场不布置试验室,只配备试验人员负责对本合同工程使用的材料(如水泥、骨料、外加剂、钢材、钢筋、锚杆以及工程指定的其它材料等)和混凝土进行取样送检,并将材料试验报告报送监理人;当监理人需要对上述各项材料进行抽样试验时,负责向监理人提供试验材料的各种试件。

2.8.4综合物资仓库

综合物资仓库租用原大坝施工物资仓库,主要存放本标段施工所需的防潮湿、防日晒及防雨淋的施工物资,布置包括劳保仓库、工具配件仓库、小型机电设备仓库、机械设备所需的润滑油、液压油、机油等、办公室、值班室及部分材料堆放场。

2.8.5袋装水泥仓库

袋装水泥仓库布置在综合仓旁,建筑面积为40m2,为前期临建和混凝土拌合等储存袋装水泥。

本标段不设置油库,施工用油料由附近加油站供应。

本标段不设置炸药库,如需爆破,根据现场业主代表介绍施工用炸药由开阳县民爆公司提供。2.8.6建筑特性及主要工程量

生产辅助车间的建筑特性参见表2.8-8。 2.8.7污水处理

19 / 35

生产生活废水全部经过处理,多重复利用,尽量少排,处理后达到排放要求

13

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件后再排放。 2.8.8生活垃圾处理

在办公、生活区、生产辅助设施区设多个垃圾桶、垃圾箱,安排专职队伍每天对生活、生产垃圾进行收集,集中后的生活、生产垃圾通过垃圾运输车及时清运至业主、监理指定的地点集中处理。

施工区和生活区的卫生设施以及粪便需及时进行消毒、化粪处理,粪渣、废渣及时清运至渣场或监理人指定的其它地点掩埋。

对生活垃圾应尽量减少暴露在空气中的时间,以免垃圾在空气中孳生蚊蝇、飘散和受暴雨洪水冲刷污染环境,必要时按照监理人的指示,采取喷洒药物、设置排水、覆土等措施。

2.8.9施工期水土保护措施

本标段责任范围内的生活区、施工场地采取设截水沟、排水沟、排水涵管,边坡采取贴坡混凝土、菱形框架混凝土等措施进行防护,同时对生活营地、生产区周围开阔地带种植树木或草籽,以防止生活、施工范围内的新增水土流失,做到在扰动的地表范围内,其水土流失强度小于现状水土流失强度。

临时设施,除合同另有规定外,在工程完工后的规定期限内拆除,并清除施工区和生活区及其附近的施工废弃物及建筑垃圾等,清理的废弃物、垃圾堆放至监理人指定的掩埋场。

2.8.10施工区空气降尘措施

对混凝土拌和系统等主要灰尘区设置专用的降尘喷雾水管,施工道路派专人负责洒水降尘工作。

20 / 35

2.8.11施工期环境美化

施工期间向当地村民购置部分花草对施工区、生活区进行美化处理,工程完工后再按设计或业主要求对种植的树木花草进行清理转移。

2.9施工消防

本标拟在生活营区、各类仓库、加工厂、拌和系统,特别是油库设置消防设施,消防设施设置情况见表2.9-9。

14

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件 2.10施工保险

水电站工程施工安全因素复杂,我公司施工过程中严格将按安全操作规程进行工程施工;同时我公司中标后除按业主要求项目进行设备、人员保险外,还将对未参保的设备和人员投保,充分维护劳动者的权利。

15

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程技术文件3.施工进度计划

3.1编制依据与原则 3.1.1编制依据

(1)《格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程招标文件》; (2)现行有关水利水电工程施工规范、标准、定额;

(3)结合本工程现场地形、地质确定的各项工程施工方案:;(4)我公司多年的施工经验和积累。

3.1.2编制原则

21 / 35

根据本合同工程的施工特点,结合我们在以往类似工程中的施工经验,初拟施工进度编制原则如下:

(1)满足工程总进度要求; (2)满足工程控制性工期要求; (3)抓住关键线路,突出重点;

(4)优化资源配置,充分体现均衡施工的原则。 3.2招标文件施工总进度要求 3.2.1工程开工及总工期

本合同工程开工时间为2014年4月1日,完工时间为2015年5月25日,总工期55天。

3.2.2控制性工期

根据对本工程招标文件提供的工程信息分析结合我公司的能力,施工计划编制的控制性工期详见表3.2-1。16

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件3.3施工总进度计划安排

根据我公司编制的投标施工组织设计,本合同工程2014年5月25日完成。

3.3.1施工准备及场内交通工程

一旦宣布我公司中标,我们将立即安排人员和设备进场,尽快展开临时设施修建工作。

进场后充分利用现有道路和场地条件,2015年4月3日前使施工便道初步具备通车条件,2015年4月25日完成EL.637.5m以下工程修复。

3.3.2施工进度安排

22 / 35

(1)2015年04月07日完成施工准备; (2)2015年04月05日,回填部位表层清理

(3)2015年04月15日完成EL.637.5m以下石渣回填; (4)2015年04月17日完成护坡混凝土基础开挖;

(5)2015年04月25日完成EL.637.5m以下护坡及基础混凝土施工;(6)2015年04月30日完成EL.637.5m~3#公路高程石渣回填施工;(7)2015年04月30日完成河道疏浚施工;

(8)2015年05月07日完成3#公路内侧挡墙、排水沟施工;(9)2015年05月12日完成3#公路平台以上石渣回填施工;(10)2015年05月15日完成菱形框架修复施工;

(11)2015年05月19日完成EL.637.5m~3#公路高程护坡混凝土施工; (12)2015年05月22日完成路面混凝土施工; (13)2015年05月25日完成清理验收工作; 3.4施工关键线路

本合同工程的关键线路为:

工程开工→人员、设备进场→施工便道修复→石渣回填→边坡混凝土→路面 17

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件混凝土施工→场地清理→工程完工。 3.5工程进度控制重点及措施

本标最大的特点就是工期紧,任务重;边坡石渣回填对护坡混凝土施工有较大影响。石渣回填、河道疏浚、是本工程进度控制的重点。

23 / 35

3.6工期保证措施 3.6.1施工组织保证措施

从管理构架入手,理顺各职能管理部门负责人之间的关系,建立精简、高效的组织体系,使工程进展过程中的各种信息流得以高效、快捷地上传下达,并及时地对进度计划作微幅调整,优化资源配置,使进度偏差控制在较小的范围内。

(1)计划合同部负责人

负责工程总进度计划,月、周进度计划的编制,制定工程进度考核管理办法及奖罚制度。及时掌握工程进展情况的汇总信息,对总进度计划实施动态控制;参加监理人定期召开的进度会议,接受监理人的指示和协调;必要时根据监理人指示对工程进度计划进行调整。

(2)工程技术负责人

根据计划合同部下达的月进度计划和工程实际进展情况制定周计划,下达给各工区,并监督实施;根据工程进度考核管理办法,对各工区执行奖罚措施;接受各工区关于工程进度的合理化建议并适时传达给计划合同部。

(3)工区或工段负责人

是周进度计划的具体执行人,和工程进展信息资料的收集、整理、反馈人,接受工程部的安排、监督,和奖罚,并对工程进度提出合理化建议。

由于工区是进度计划的实施者,必须采取有效措施,提高一线作业员工的积极性,使进度计划落到实处。工程进度奖罚措施必须合理、可行,并及时兑现。

3.6.2技术管理保证措施

(1)认真调查、研究工程地质、水文、气象资料和市场情况,结合类似工程施工经验,制定切合工程实际的各施工阶段的技术方案、措施,以及应急技术措

24 / 35

18

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件施,做好技术交底,建立技术档案,使技术管理科学化、信息化。

(2)抓好新技术、新材料、新工艺的推广运用,充分发挥我公司在施工技术方面的优势,组织科技攻关小组和QC活动小组,及时解决施工中出现的问题、难题。

(3)对工程进展中出现的进度问题提出相应的建议和措施,必要时根据监理人指示制定切实可行的加快工程进度的措施。

3.6.3现场管理保证措施

(1)建立健全质量保证体系,确保施工质量,避免因质量事故引发工期延误。

(2)建立健全施工安全保证体系,采取有效的安全保障措施,组织好现场安全施工,搞好文明施工,创造一个安全、文明、有序的施工环境。

(3)在进度实施过程中抓住关键项目,加大人力、物力投入,特别是高峰期的投入,确保主要工序和关键线路按期完工,同时兼顾其他项目。

(4)加强人员和设备管理,提高设备和劳动生产率。

(5)充分利用好现场有关施工设备,同时根据工程进展新购或从公司内其它项目调配施工需要的设备进场,以充分满足施工需要。

(6)充分利用网络管理技术,对施工所需材料、配件进行网络查询和采购,对物资存储进行科学管理,保证正常的物资采购和供应,尽量减少因材料、配件的短缺原因造成施工延误。

(7)对工程款项进行科学管理,用好、用活资金,必要时从公司本部或采取其他手段调配充足的资金,保障施工生产对资金的需求。

3.6.4质量管理保证措施

25 / 35

我公司将按照ISO9001:2000质量管理体系标准,建立健全以项目经理为第一责任人的质量管理体系,结合工程实际,编制适合于本工程的质量计划,严格按计划中的过程、程序和项目进行实施,实行质量责任终身制,层层落实到个人,真正做到全员、全方位、全过程的有效控制。保证工程总体质量达到优良标准。消灭一切质量事故,坚决杜绝由于质量问题引起的误工、返工现象,确保工程顺利进行。

19

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件项目经理将充分授权给项目部的质量管理负责人,赋予质量管理负责人针对质量事故防范与处理的奖罚权利,让质量管理者说话有份量、管理有力度。这样将加快各道工序合格施工及验收,避免误工及返工、工序衔接拖延导致工期损失。

3.6.5施工资源管理保证措施

机电物资、综合及财务负责人,根据施工组织设计及总进度计划的要求,超前编制并落实好各阶段的人力、机械设备、材料物资及资金供应计划,确保施工进度的需要。主要的机械设备、材料物资保证有必要和足够的备用。对不适合的设备及时更换,不得影响施工,以确保施工强度的要求。

3.6.6进度管理保证措施

施工进度计划的实施与控制是一个复杂的、动态的信息的收集、处理、反馈、发布的过程,我公司将借助于计算机信息化技术、运用先进的工程管理软件(P3),施工期间我公司将以P3产生的进度计划为指导组织施工,定期(周、月)向P3录入施工实际进度信息,并将实际进度信息上报监理人核实。当计划与进度脱节时,必须运用P3,会同发包人、监理人等有关各方制订赶工计划,并将其反馈到原计划上去。计算机输出的结果将作为发包人、承包人、监理人与设计单位“四方协调会议”讨论的基础。

按工程需要配备足够的专业熟练的工程技术人员,在项目部的统一领导下,形成一个高效、科学的信息管理系统,对工程进展全过程实施动态的监

26 / 35

督、控制,并按合同要求适时地向监理人报告工程进展情况,参加监理人主持的进度会议,接受监理人的监管与协调。

根据合同文件规定的内容和期限以及监理人的指示,编制施工总进度计划报送监理人审批。经监理人批准后作为控制本合同工程进度的依据,并据此编制年、季和月进度计划报送监理人审批。在施工总进度计划批准前,按签订协议书时商定的进度计划和监理人的指示控制工程进展。

在每月开始前14d提供月进度计划报送监理人,内容和要求包括:(1)计划完成的月工程量及其施工进度形象、材料用量和劳动力安排;

(2)该月所需施工设备数量及材料计划; (3)提出该月发包人应提供的施工图纸目录等; 20

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件(4)该月施工的各工程项目的试验检验和验收计划,包括工程试验和验收应完成的各项准备工作;

(5)水泥、外加剂、钢筋、钢材、砂、石骨料等材料的需求计划。 (6)监理人要求提供的其他的内容和要求。

参加由监理人定期召开的周、月进度会议,并按合同规定的格式提交周、月进度报表,其内容包括:

(1)上周(或上月)之前合同进度计划要求和实际完成的累计工程量统计;

(2)本周(或本月)实际完成工程量统计; (3)下周(或下月)计划完成的工程量; (4)工程质量情况;

27 / 35

(5)机械设备、劳动力使用状况; (6)要求监理人协调解决的主要问题。

经进度会议协调达成一致意见后,接受监理人的监管与协调。

当工程的实际进度与合同进度计划不符时,按合同要求并根据监理人的指示在28天内提交一份修订的进度计划报送监理人审批,经监理人批准后的修订进度计划作为合同进度计划的补充文件,并遵照执行。

当施工进度计划延误时,应按监理人指示,以保证工程按期完工为前提,调整资源配置,编制赶工措施报告报送监理人审批,并根据监理人的指示积极、有效地采取得力措施加快施工进度。

3.6.7环境及文明施工保证措施

项目部将设置专人,在业主和监理工程师的统一领导下,积极处理好与地方的关系,加强与施工有关各方面及其他施工单位的联系和沟通,加强自身人员的管理,并根据现场情况对有可能影响工程进度的因素进行预控,争取较好的施工环境,促进施工顺利高效进行。

3.6.8施工安全保证措施

在工程施工中,认真贯彻执行国家有关安全生产的方针、政策、法律法规,严格遵守发包人的安全制度,以施工安全目标为中心,采取可靠措施,建立健全安全生产保证体系,落实以项目经理责任制为主的各级安全生产责任制,重奖重

21

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件罚,切实制订内部安全管理实施细则,并贯彻于施工全过程,确保施工安全,以促进各阶段施工目标的顺利、按期完成。

4.组织机构及资源配置 4.1施工进场

28 / 35

为了加强统一管理,保证工程质量和工程进度,如果我公司中标,我公司将迅速组建格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程施工项目经理部,组织精干的工程管理和施工技术队伍,抽调熟练技术工人,投入先进、实用的施工机械设备进入施工现场,以确保按期、优质、高效地建设好本工程项目。

在签定中标合同书后,由我公司成立的工程项目经理部和公司相关职能部门配合,立即组织安排第一批工程管理和施工人员迅速进场。第一批人员和设备在接到中标通知书后的2日内抵达现场。部分人员、设备将根据本工程施工进度安排和实际情况,结合我公司本部的人员、施工机械设备调配计划,制定详细的机械设备转运方案,分批次进入工程现场。

4.2现场施工准备

在第一批施工人员、设备和材料进场后,立即按计划进行现场的施工准备工作。(1)组织工程技术人员踏勘现场、收集地形、水文气象、工程地质和水文地质等资料,组织管理人员和工程技术人员进行实施阶段的施工组织设计,对分部和分项工程将采取广泛论证和方案评估比较的办法,在征求监理工程师意见情况下,在“高质量和最佳效益”为最优方案的前提下进行主体工程施工前的内业准备工作,并在规定的日期前报送监理工程师审批。正式开工前,会同设计单位、监理单位进行技术交底,充分了解设计意图,并据此来指导施工。

(2)迅速组织工程测量人员校测由监理工程师提供的测量基准,并按《水利水电工程施工测量规范》(SL52-93)和本工程施工放线精度要求测设用于本工程施工的测量控制网,并将施工控制网资料报送监理工程师审批,对测设的网点和

22

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件增设的控制网点进行诸如设置防护网、竖立标志与警示牌等措施进行有效的保护。

29 / 35

(3)了解当地生活、生产资源的供应情况和当地建筑材料的产地、产量、质量、规格、运输方式及价格情况;施工电源接线点的位置、电源电压、容量及电源离施工现场的距离。了解当地的医疗、主、副食供应、日用品及燃料供应情况以及当地传染病危害情况,并制定预防措施。按照已通过监理工程师审批的临时工程施工设计方案,组织场内临时道路、生活和办公设施、施工辅助企业、施工风、水、电系统、仓储系统等临时设施的建设。(4)对有火灾隐患的施工区域,在当地消防部门指导下,提前在主体开工前设置安全防火带。在可能由于施工造成的植被破坏或有水土流失隐患地段,我方将有责任和义务在施工前和施工期间进行保护。

(5)按计划采购施工用材料、设备及零配件等。收集材料供应、运输的有关资料。按合同工期要求,组织落实好本标工程建筑材料的采购及运输工作,投入本标工程的各种施工机械投入施工前均需进行检修、保养工作,保证机械完好,并备足备品、备件。

(6)组织专职质检人员、安全人员编制本工程质量文件、施工安全措施文件和《安全防护手册》,并对所有施工人员进行考核。

(7)和当地政府及有关部门进行沟通交流,取得他们的支持,与建设单位一起向当地群众大力宣传本工程的重要性,最大限度地争取当地群众的支持与配合,为工程施工创造良好的外部施工环境。

4.3现场组织机构设置

接到中标通知书后,我们将立即组建项目部及作业队,并作施工准备,动迁计划。根据施工总进度计划安排,施工高峰人数为54人。组建项目部,项目部组织机构图4.3-1。

组织机构职能说明: 23

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件

30 / 35

副经理

(分管生产、安全)

总工程师(分管技术、质量)项目部项目经理 总经济师

质量、安全、施工) 工程管理部(技术、 开挖队队长 资

、商务合同) 合同物质管理部(物 综合管理) 综合管理部(后勤试 验 室 负责人 混凝土浇筑队长 基础处理队队长 机电运行队长队长 综合队队长 班(组)长操作工人 24

31 / 35

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件图4.3-1组织机构图 (1)项目经理

项目经理是本合同工程施工的全权代理人,对本工程施工行使管理权,对项目目标的实现承担全部责任。

项目经理的基本职责主要有:确保项目目标的实现全面负责工程施工期间的各种重大决策的确定和对外关系协调,负责对工程质量、安全、进度实施控制,协调项目部各职能部门的关系,保证让业主和监理人满意;制定项目总体控制计划和阶段性目标;组织精干高效的项目管理班子;及时决策;履行合同义务,监督合同执行,处理合同变更,对项目部各职能部门的工作进行考核和评价。

(2)项目副经理

协助项目经理全面负责工程施工期间各种重大决策的制订、实施和对外关系协调,协助项目经理对工程的质量、安全、进度、成本实施控制,协调项目部各职能部门的关系。受项目经理委托,在项目经理不在现场的情况下代理项目经理的职责。

(3)项目总工程师

总工程师受项目经理领导,对全项目工程质量、施工技术、测量、试验等工作负全面技术责任,指导工程技术人员开展有效的技术管理工作;负责新技术、新工艺、新设备、新材料及先进科技成果的推广应用,解决工程施工中有关技术难题,督促检查各项质量计划的实施。主持项目工程索赔方案的制订、审核、报批和组织实施。

(4)总经济师职责

受项目经理领导,负责项目的生产经营工作;负责主持制订和审核项目经营计划、生产计划,明确各项经营考核指标;负责主持项目合同评审工作和工程分包工作;主持项目经济活动分析,及时掌握项目生产经营动态,并定期向

32 / 35

项目经理汇报;主持项目对外结算、经济核算和调价补差工作,主持项目工程索赔方案的制订、审核、报批和组织实施。

(5)部(室)职责 1)工程管理部

在总工程师的直接领导下,负责本项目施工的技术指导、工程测量、工程试

25

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件验等工作,负责编制施工组织设计,进行施工技术交底,及时发现并处理施工中的技术问题。负责工程施工质量安全管理工作;组织编制项目质量计划,并督促、检查有关部门执行质量计划,协调有关部门的质量管理工作;收集、整理有关质量信息,掌握质量动态,进行质量分析和评价;对施工过程中的质量进行检查,开展工序控制,严格完工检验。

负责生产安排、调度、协调工作,负责工程施工阶段观测记录工作。测量队:负责工程控制网点的复核和加密及其维护、工程施工的测量放样、测量原始资料的整理;参与工程施工阶段观测记录工作。试验室:负责项目工地计量设备及仪器管理工作;负责混凝土生产质量控制,参与施工期观测工作;负责对工程材料的物理、化学性能的检验和试验;负责对混凝土、砂浆等混合物的配合比试验和控制等工作。

负责工程施工的安全、环保工作,编制施工安全及环保措施计划,定期进行施工安全及环境保护的检查,及时提出整改措施并监督落实。加强火工产品的运输、使用、管理等。

2)合同物资部

负责制订生产经营管理办法及制度;负责项目合同管理和分包工程评审签约工作,负责编制生产经营工作计划和年、月生产经营统计报表,负责对内对

33 / 35

外的工程款结算工作。负责财务管理、成本控制、变更索赔,工资发放、编制财务报表、工程决算等工作。

负责编制配件、仪器设备采购计划,负责配件及仪器设备的采购、运输及保管工作;负责项目施工所需仪器设备物资采购及施工设备的进退场工作;负责对报废机械、设备的鉴定和处理;负责对施工设备维修进行技术指导。

3)综合办公室

负责施工人力资源的调配以及施工人员技能培训、岗位培训及其考核工作;负责项目文件、资料的收发;负责征地拆迁、负责项目的后勤工作和对外联络、接待工作。

4.4具体管理措施

我公司严格按项目法管理,确保项目顺利实施。格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程项目部,项目经理直接向公司总经理负责,并对项目的

26

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程

技术文件质量、安全生产、文明施工及经营管理全面负责,同公司签定项目经营承包责任合同书,项目经理、副经理、总工个人收入同项目经营挂钩。每年年底按项目的安全、质量、生产计划及经营等指标考核兑现。

项目经理对项目部各部门、作业队第一责任人签定内部经营承包合同,并按安全、质量、生产计划考核兑现收入。

项目经理由公司总经理聘任,并对副经理、总工的任免有建议权,对各部门、工区负责人有任免权,对项目资金、材料设备调配、使用有决策和执行权。

项目资金的支付由项目经理签字确认后实施,资金的使用以确保项目的生产需要为原则。

34 / 35

27

格里桥水电站厂房上游侧边坡坡脚水毁修复处理工程 技术文件5.土方明挖 5.1工程概况

本标的土方系指表土、回填石渣、河道疏浚等,无需采用爆破技术而可直接使用手工工具或土方机械开挖的全部材料,。

土方明挖包括本合同工程的贴坡挡墙基础开挖以及监理人指明的其他土方明挖工程。其开挖工作内容包括:准备工作、场地清理、完工验收前的维护,以及将开挖可利用或废弃的土方运至监理人指定的堆放区并加以保护、处理等工作。土方开挖及填筑工程量见表5.1-1。

5.2施工布置 5.2.1道

35 / 35

因篇幅问题不能全部显示,请点此查看更多更全内容